RALEIGH, N.C. (WHKY) - 49 attorneys general are pushing the Federal Communications Commission (FCC) to…
Microsoft says redesigned cooling systems will reduce water use at its Catawba County data centers by as much as 80 percent.
City Of Hickory
City Of Hickory
Microsoft Says New Cooling Technology Will Dramatically Cut Water Use At Catawba County Data Centers
HICKORY, N.C. — Microsoft says its four data centers under construction in Catawba County will use far less water than originally projected after redesigning the facilities with newer cooling technology.
The company says engineering advances made since its 2022 planning estimates have reduced projected peak water demand by 75 to 80 percent and wastewater demand by 85 to 90 percent. Microsoft says the earlier numbers reflected maximum capacity set aside for long-term planning rather than expected day-to-day usage.
The updated design relies primarily on liquid cooling technology, which circulates coolant in a closed-loop system. Because the liquid is continuously reused, Microsoft says little to no water is lost through evaporation, making the facilities more energy and water efficient.
When Microsoft first outlined the project in 2022, planning documents showed the Hickory and Maiden campuses could require up to 1.8 million gallons of water per day at maximum build-out. The company now says those estimates no longer reflect the current design.
Microsoft also says it achieved its goal of becoming “water positive” in 2025, five years ahead of its original 2030 target, by replenishing more water than it consumes globally.
Local officials say they are not concerned about the revised projections. Hickory City Manager Warren Wood has previously said the facilities are not expected to be major water users and will provide significant tax revenue while requiring relatively few city services.
A joint statement from Catawba County, Hickory, Conover and Maiden says the facilities are expected to use approximately one percent of Hickory’s daily water production capacity once fully operational. Microsoft has also announced it intends to forgo previously approved tax incentives. The company committed to investing at least $1 billion in four Catawba County data centers, with building permits already exceeding $900 million.
Short Caption
Microsoft says redesigned cooling systems will reduce water use at its Catawba County data centers by as much as 80 percent.